Wonder if we could install 1 of those . . . 3/08
| Let's put the Wind Turbine where Shaar is hiding behind that 2x4
5/26/08
| Neil starts a test hole for the foundation 6/6/08
|
Michal takes a turn at the shovel 6/6/08
| PLANS FALLING INTO PLACE SO WE APPLY FOR BUILDING PERMIT 6/13/08 (FRIDAY)!
| The (almost) last shovel full leaves the foundation excavation 6/14/08
|
Leveling the base for the foundation structure 6/14/08 ("Test hole" until we get the building permit)
| 7/8/08 Building permit issued. 7/9/08 start on SMarT foundation
| Inserting FRP re-bar in lower stanchion (FRP is Fiber Reinforced Polymer)
|
Placing steel rebar over stanchion, resting on FRP
| Placing FRP rebar on upper stanchion
| Injecting expanding foam to secure FRP rebar
|
Assembly suspended from ceiling
so can place anchor bolts and
template over rebar stanchion. Upper steel rebar in place
| Copper grounding coil in place 2-1/2" above base of Concrete
7/10/08
| Sonotube attached. Rebar rings secured to anchor bolts. Securing wires to steady base.
|
Transporting to excavation
|
Lowering into place
|
Final check before last 2" down
|
Re-siting on foundation blocks
| 7/12/08 Alligned, leveled, secured, electrical conduit in place, ready for inspection and concrete pour
| Neil, Gerald, Gene & Aaron ready for the first mud 7/22/08
|
Neil braces, Gene gets into his work, Gerald controls flow
| About to cover base
| Gene makes sure base is filled solid
|
About half full
|
Insuring Mud reaches all nooks and crannies
| Hand work to fill the raised center column
|
Aaron makes stepping stones with the extra mud
|
Let it cure for a few weeks
| 9/2/08-Home from vacation Foundation cured and ready for
tower
|
Hand dug trench-top 9/9/08
| Hand dug meter end
| Mike starts Bobcat trench
9/11/08
|
Mike trenches - one of his 3 dogs inspects
| Trench end - meter pole
| Where-da-heck is the end of that conduit? 9/13/08
|
Unrolling cable 9/15/08
| Success! Cable thru conduit in foundation
| Trench filled in - Michal adds final touch 9/20/08
|
Nested Tec-Wind tower sections
ready to be unloaded. William, Glen (truck driver), John FVFR Vol - all helping 9/22/08
| Off come the tower sections
| Separate top section unloaded the old fashioned way
|
Loading heavy nested tower sections for the run uphill
| Starting up the driveway
| 3/4 mile later all sections still on!
|
Almost to top . . .
| Nested sections parked
| Top section almost there
|
Sections un-nested & ready
for de-burring and assembly
| De-burring joints with file 9/25/08
| 3 of 5 tower sections in place (sort of), ready for assembly. Oh, and the Aspen are turning. 9/28/08
|
Tightening hinge base with 1st tower section temporarily
in place 10/2/08
| Assembling Gin Pole 10/2/08
| Raising Gin Pole to vertical
10/3/03
|
Dave & Janice Pistole arrive just in time to help assemble
and raise the tower - THANK YOU!
| Attaching snatch block to truck "anchor" 10/4/08
| Janice & Dave prepare to pull electric cable to top
|
Checking lift cable
| Tower starts up
| Michal's view of lift. She held brakes on "anchor truck"
|
Checking bolt allignment
| Pulling the last few feet by hand
| We did it - well, with the help of Janice and Michal!
|
Tighten those nuts!
| Voltair tower is up - waiting for arrival of turbine
| Driving 2nd of 2 grounding rods (a grounding coil is also
in base of foundation)
|
Removing nuts so tower may be lowered to attach wind turbine 10/21/08
| Michal ready to start backing to lower tower after tower is tipped by hand
| Lifting gin pole to tilt tower. Lowering cable attached to
tractor
|
Almost to tip point. 1 more lift and strain should be on tractor cable
| Michal controls decent on
way down
| Almost down on blocks
|
Down, braced and ready for turbine arrival
| Voltair arrives! (Nice of it to snow today, eh?) 10/22/08
| Is that all there is? (Well, plus the blades.)
|
Ready to wire, test & bolt to tower
| Russ connects cable. Even checks directions!
| Successful "power on" test!
|
Time to quit for the day. 22 degrees and snow.
| Torque those bolts 10/23/08 (Nice left boot . . .)
| Assembling wind blades to hub 10/24/08
|
Torque 'em!
| Filling last of trench after Russ finished electrical 10/26/08
| Rotate turbine so can attach blade assembly
10/27/08
|
Blade assembly into position
|
Align with shaft
| Spin blades tight onto shaft
|
Attach nose cone
| And yaw shield
| Required both tractor and truck to start tower up
|
Almost up-tractor only now
| Up! Secure those nuts!
| Tighten 'em
|
Just need final inspection and 2-way meter install
|
Building inspector Robert-final sign off on project! 10/28/08
|
Carl from electric Co. (IREA) advises WE PASSED the lock- out test! 11/4/08
|
Michal throws the switch -
| - and Voltair is generating
| The idea was 1st discussed in March, '08. We began generating some of our own electricity 11:53 am, 11/4/08!
Thanks to all who helped.
|